Construction of Sardasht project beams and installation by pushing method (8 spans of 49 meters) weighing 1500 tons – February 2015
General specifications:
Total bridge length: 370 meters (8 spans)
Total weight of metal structure: 1350 tons
Installation method: 7 pushing spans – 1 installation span with crane
Project end: February 2015
Location: On the Zab River (Baneh – Sardasht Road) – West Azerbaijan Province