Construction and installation of the overpass bridge of the Semnan Industrial Park, 38 meters long (3 spans) and weighing 200 tons – July 2008

General specifications:

Total length of the bridge 38 meters with a span of 10 + 18 + 10 meters

Total weight of the metal structure 200 tons

Project started in February 2009 and completed in July 2009

Pictures in the following article