Construction and installation of the Rood Shur Railway Bridge Project – 12 spans of 50 meters, 1460 tons – May 2015
General specifications:
Total bridge length: 600 meters with 50-meter spans
Total weight of the metal structure: 1460 tons
Installation method: with crane
Project start in February 2013
Location: on the Shur River – Tehran-Hamedan Railway
Pictures to follow