Construction of Sardasht project beams and installation by pushing method (8 spans of 49 meters) weighing 1500 tons – February 2015

General specifications: Total bridge length: 370 meters (8 spans) Total weight of metal structure: 1350 tons Installation method: 7 pushing spans – 1 installation span with crane Project end: February 2015 Location: On the Zab River (Baneh – Sardasht Road)…

Read MoreConstruction of Sardasht project beams and installation by pushing method (8 spans of 49 meters) weighing 1500 tons – February 2015

Construction and installation of the Rood Shur Railway Bridge Project – 12 spans of 50 meters, 1460 tons – May 2015

General specifications: Total bridge length: 600 meters with 50-meter spans Total weight of the metal structure: 1460 tons Installation method: with crane Project start in February 2013 Location: on the Shur River – Tehran-Hamedan Railway Pictures to follow

Read MoreConstruction and installation of the Rood Shur Railway Bridge Project – 12 spans of 50 meters, 1460 tons – May 2015

Construction and installation of Hashtgerd overpass with a span of 20+50+20, consisting of 4 box girders, 90 meters long, 2 meters wide, 2 meters high, weighing 600 tons – September 2014

General specifications: Total length of the bridge: 90 meters, with a span of 20+50+20 meters Total weight of the metal structure: 600 tons Installation method: with a crane Project started in September 2003 and completed in September 2004 Location: on…

Read MoreConstruction and installation of Hashtgerd overpass with a span of 20+50+20, consisting of 4 box girders, 90 meters long, 2 meters wide, 2 meters high, weighing 600 tons – September 2014

Construction and installation of the Qazvin-Rasht-Anzali railway bridge project (km 700+101) 25 50-meter spans + 5 3-meter spans (installation of 10 spans by advancing) Bridge length 1500 meters (30 spans) weighing 3500 tons – May 2015

General specifications: Total bridge length 1500 meters with 50-meter spans Total weight of the metal structure 3000 tons Installation method: 10 advancing spans and 20 spans with crane Project start February 2017 Location: On Sepidroud Lake in Manjil city on…

Read MoreConstruction and installation of the Qazvin-Rasht-Anzali railway bridge project (km 700+101) 25 50-meter spans + 5 3-meter spans (installation of 10 spans by advancing) Bridge length 1500 meters (30 spans) weighing 3500 tons – May 2015

Construction and installation of Kermanshah-Khosravi railway bridge (km 615+5) – 4 spans of 28 meters, weighing 70 tons – July 2013

General specifications: Total bridge length: 112 meters (4 spans of 28 meters) Total weight of metal structure: 70 tons Installation method: Installation with crane Project start: July 2013

Read MoreConstruction and installation of Kermanshah-Khosravi railway bridge (km 615+5) – 4 spans of 28 meters, weighing 70 tons – July 2013

Construction and installation of metal beams of the Western Railway Bridge (km 209 and 239) – 9 spans of 30 meters, weighing 400 tons – September 2012

General specifications: Total bridge length: 270 meters (9 spans of 30 meters) Total weight of the metal structure: 400 tons Installation method: Installation with a crane Project completion: Location: Western Railway (Kermanshah)

Read MoreConstruction and installation of metal beams of the Western Railway Bridge (km 209 and 239) – 9 spans of 30 meters, weighing 400 tons – September 2012